click to enlarge |
| DATE:
September 2007 |
LOCATION: Jubail
Saud: Arabia |
PROJECT: Installation
of 2No 8in HDPE pipes, 12 boring under
highways. |
GROUND CONDITIONS:
Sand |
LENGTH OF BORINGS:
60m - 110m long |
| RIG SIZE:
HDD American Augers DD8 (45 TON). |
|

click to enlarge |
| DATE:
April 2007 |
LOCATION: Jeddah
Saud: Arabia |
PROJECT: Instalation
of 18in and 6in steel pipes, 9 boring
under highways |
GROUND CONDITIONS:
Sand/Gravel |
LENGTH OF BORINGS:
60m - 140m long |
| RIG SIZE:
HDD American Augers DD8 (45 TON). |
|

click to enlarge |
| DATE:
October 2006 |
LOCATION: Saudi
Arabia |
PROJECT: Drilling
under sand dunes. 20in Steel. |
GROUND CONDITIONS:
Very compact sand. |
TIME SCALE: 4 months. |
LENGTH OF BORINGS:
4No - 2No 800m 2No - 1700m |
|
RIG SIZE: American
Augers DD625 (285 TON). |
|

click to enlarge |
| DATE:
October 2006 |
LOCATION: Saudi
Arabia |
PROJECT: Wireline
Steeling Work. 800m - 1700m long. |
TIME SCALE: 10 day
per crossing |
EQUIPMENT: Tensor
Steering Tool with True Track. |
| NOTE:
Drilled out on line within 300mm on
all crossings. |
|

click to enlarge |
| DATE:
March 2006 |
LOCATION: India |
PROJECT: Installation
30in + 6in steel oil pipeline. |
TIME SCALE: 2 months. |
LENGTH OF BORINGS:
4No 380m and 440m |
|
RIG SIZE: American
Augers DD625 (285 TON). |
|

click to enlarge |
LOCATION:
Qatar |
PROJECT: Insallation
of 3No - 160mm with 3 Borings per site. |
| GROUND CONDITIONS:
Hard Rock |
TIME SCALE: 6 months. |
| LENGTH OF BORINGS:
50m - 120m long - Total ±25No. |
SIZE OF RIG: Ditch
Witch 40/20 AT. |
|
| UAE
NASR Iragation Company |

click to enlarge |
| DATE:
October 2005 |
LOCATION: UAE |
PROJECT: Installation
of 1No 900mm pipe HDPE |
| GROUND CONDITIONS:
Mud and Stone |
TIME SCALE: 2 months. |
LENGTH OF SHOTS:
1No 660m long |
| RIG SIZE:
American Augers DD625 (285 TON). |
|

click to enlarge |
| DATE:
October 2004 |
LOCATION: Saudi
Arabia |
PROJECT: Installation
of 750mm steel pipeline |
| GROUND CONDITIONS:
Sand and Stone |
TIME SCALE: 1 month. |
LENGTH OF SHOTS:
1No 630m |
| RIG SIZE:
American Augers DD625 (285 TON). |
|
| Hogenboom
/ 24 Seven Electric |
 |
| DATE:
October 2002 |
LOCATION: Hoddesdon,
Herts. |
PROJECT: Installation
of 3 number 180 O/D PE sleeves under
landfill site which had contamination. |
GROUND CONDITIONS:
Gravel and clay. |
TIME SCALE: 4 weeks
drilling. |
LENGTH OF SHOTS:
405m 392m 385m. |
| I.L.C. used a 200 gallon
per minute recycling system so as not
to incur a high cost to our client for
slurry removal. |
|
| Electron/
24 Seven Electricity |

|
DATE: September
2002 |
LOCATION: Huntingdon
A14 |
| PROJECT:
Installation of 180mm pipes for electric
cables. |
GROUND CONDITIONS:
Gravel |
TIME SCALE: 2 weeks. |
LENGTH OF SHOTS:
8 shot, single way, 100m length.
2 shot, 3 way, 100m length.
|
| SIZE OF RIG:
40/20 Ditch Witch. 18 ton Rig. |
| I.L.C. incurred very
bad ground conditions for drilling,
which was large gravel. The use of special
additives to the mud was needed to hold
the bore open, so as to pull the product
in without bore coming in on the pipe. |
|
| John
Mowlem - Civil Engineering |
 |
DATE: March 2002
|
LOCATION: Exeter |
| PROJECT:
180mm Pipe pumping sewer pipe under
SSI site (Site of Scientific Interest).
|
GROUND CONDITIONS:
Clay |
TIME SCALE: 2 weeks. |
LENGTH OF SHOTS:
460m |
| SIZE OF RIG:
70/20 Ditch Witch, 35 ton. |
|
The SSI site was a Bird Sanctuary.
Work carried out caused minimum disruption
to the inhabitants. |
|

 |
DATE: November 2001
|
LOCATION: River
Teign, Devon. |
| PROJECT:
180m Single Way. |
GROUND CONDITIONS:
Sandstone. |
TIME SCALE: 2 weeks. |
LENGTH OF SHOTS:
510m. |
| SIZE OF RIG:
Ditch Witch 70/20 |
| The shot had to be drilled
in a 6mm wide window between the bridge
and BT’s Fibre optic route, running
parallel with the bridge. |
|
186k Nacap |
Aquila |
Bechtel |
British Waterways |
Electron |
Environmental Agency |
Hogenboom Infrastructure |
Kenton Utilities |
Lawrence Pipe lines |
Marconi |
McNicholas Construction |
MKI WorldCom |
Morrison Construction |
Mowlem |
J. Murphy & Sons |
NTL |
Railtrack |
Transco |
ARAMCO (Saudi) |
Saudi Telecom |
Techint |
NACCAP (SRB) |
|
|
|
|
|
 |
|